GNC Water Meter
Neenah, WIOverview
The customer for this project requested a meter change that would require a shutdown of the water main to the entire GNC plant. During planning meetings, a minimal down time was identified as a priority for the owner. Pre-fabrication was seen as essential to ensure the meter swap could be completed in the short eight-hour timeframe. The project was completed under budget and the customer was highly satisfied with the entire project process.
—